What's New: Project Milestones

Norfolk County Agricultural High School (The ‘Aggie’)
Category: Project Milestones

Phase I construction is underway:  site perimeter enclosure / tree cutting / clearing have commenced.  Site utility work will commence 04/17/12;  site and structural excavation for four “new” buildings will commence week of 04/23/12.  Phase I building construction completion is forecast in May, 2013.